The New Mining Code was adopted by the Congolese Parliament on 27 January 2018 and promulgated by the president of the DRC on 9 March 2018. The implementing measures of the New Mining Code are set forth in the Mining Regulations adopted in June 2018.
The DRC is a member of several international organisations, including the World Trade Organization, the World Bank Group, the Multilateral Investment Agency, and the International Centre for Settlement of Investment Disputes. The DRC has also ratified the 1958 New York Convention on the recognition of foreign arbitral awards.
In addition, the DRC voluntarily adhered to the Extractive Industries Transparency Initiative criteria, and has entered into several bilateral investment treaties and into a convention for the avoidance of double taxation with Belgium.
Additionally, with the stringent UK Bribery Act and US Foreign Corrupt Practices Act in force, it is essential for any company doing business in the DRC to seek professional commercial and legal guidance to mitigate business and regulatory risks. Section 1502 of the US Dodd–Frank Wall Street Reform Act and the new EU Conflict Minerals Regulation are also relevant for businesses active in the DRC. Depending on the type of mineral traded (tin, tungsten, tantalum and gold), these laws impose extensive supply-chain due diligence obligations on both upstream and downstream companies.
At the regional level, in July 2012 the DRC joined the Organisation for the Harmonisation of Business Law in Africa (OHADA). OHADA law can only benefit further investment by providing companies doing business in the DRC with a single, modern, flexible and more reliable business law framework, which already applies in 17 OHADA Member States and which supersedes previous or subsequent national legislation. OHADA law is of particular interest to mining companies, as it primarily covers commercial, corporate, loan-guarantee, accounting and arbitration law. OHADA law entered into force in the DRC on 12 September 2012. In addition, a one-stop shop for business start-ups was instituted and shows encouraging development.
Congolese law, which is based on civil law and closely modelled on Belgian law in particular, will remain applicable in areas not governed by OHADA law. It will thus be of paramount importance to understand the myriad applicable pieces of legislation to properly navigate the remaining bureaucratic, legal and, especially, cultural and linguistic hurdles.
The Mining Cadastre receives applications for mining rights, grants mining rights and keeps records of mining rights, among other functions. Moreover, the DRC has created a national transparency initiative committee with respect to the management of extractive industries in the DRC. Any regulation is issued by the Ministry of Mines, which supervises mining activities at the national level. At the highest level, the President of the DRC is empowered to enforce the mining regulations and to classify mineral substances as reserved mineral substances, if applicable.
Mining rights and required licences and permits
i IntroductionUnderground minerals belong exclusively to the state. However, any private party may be authorised by the state to engage in mining activities (from exploration to exploitation and distribution), provided that specific objectives of eligibility, priority and capacity criteria set forth in the Mining Code are met. The types of mining permits available in the DRC are research permits, exploitation permits (including small-scale mines) and tailing exploitation permits. Specific legislation regarding artisanal mining also exists.
Companies that wish to develop mining activities in the DRC are required either to incorporate a Congolese company or to elect domicile with a 'mining agent' as a condition of eligibility to obtain an exploitation permit. In addition, to be eligible for a mining permit, companies are obliged to either form a joint venture with a state-owned company (such as Gécamines) that already holds the necessary permits, or freely assign a mandatory 10 per cent stake of its share capital to the DRC.
ii Surface and mining rightsAny person wishing to engage in prospecting or reconnaissance activities must make a prior declaration to the Mining Cadastre and seek a prospecting permit. This permit entails no priority whatsoever in relation to potential future exploration or exploitation rights.
An exploration permit may be granted to any eligible private company for a period of five years, renewable once for the same duration, with respect to all mineral substances (Article 52). To be eligible for an exploration permit, a company must demonstrate a minimum financial capacity of at least five times the total amount of the annual surface rights payable for the area covered by the exploration permit (Article 58). The surface rights amount to US$5.89 per square metre (Article 397). In addition, the company will have to submit a rehabilitation and mitigation plan before starting any research activity. There are specific obligations for maintaining the permit, including the requirement to start exploration work within one year of delivery of the permit (Article 197).
Should the holder of a research permit demonstrate through a feasibility study the existence of an economically workable ore deposit (including tailings, for which specific permits exist) and sufficient financial capacity for the development, construction and exploitation of a mine, the Minister of Mines may grant an exploitation permit for a duration of 25 years, renewable for successive periods of 15 years. The exploitation permit may be refused by the Minister of Mines only for specific reasons, which are exhaustively listed in the Mining Code. Obtaining an exploitation permit obliges the operator to transfer to the state a free carry participation of 10 per cent of the operator's share capital (Article 71). In practice, however, operators that are engaged in joint ventures with state-owned permit holders, such as Gécamines, are not required to transfer 10 per cent of their share capital to the state.
In addition to exploration and exploitation permits, the Mining Code contains specific provisions with respect to artisanal or small to very small-scale mining rights, and quarry rights. Quarry rights relate to construction materials rather than mineral substances.
The timeline for obtaining an exploration or exploitation permit is as follows.
The Mining Cadastre has 20 working days to examine the request and to make a decision (Article 40). Following this, the Directorate of Mines must conduct a technical investigation. The office in charge of the protection of the environment examines the environmental impact study and the environment management plan. These reviews must be conducted within a period of time set forth in the Mining Code for each type of request (typically, for exploitation permits, within 30 working days for the Mining Cadastre, 60 working days for the Mining Directorate and 180 working days for the environmental investigation). Should any of the aforementioned authorities fail to reach a decision within the required time frame imposed by the Mining Code, the mining permit will be considered granted.
When a favourable decision is made, the Mining Cadastre will then grant the mining permit to the applicant, provided that the relevant surface rights have been paid for within 30 business days.
All mining rights are conveyable under the Mining Code. A specific right of amodiation (comparable to a long lease agreement) also entitles the holder of an exploitation permit to transfer all or part of such rights under a rental scheme. Exploitation permits can also be mortgaged. Finally, while mining rights are valid only for specified mineral substances, permits can be extended to additional minerals through specific procedures.
iii Additional permits and licencesProcessors of mineral substances who do not hold mining rights and whose activities are limited to processing activities must obtain a specific licence in this respect pursuant to the Mining Code.
iv Closure and remediation of mining projectsThe holder of a research permit will also have to submit a rehabilitation plan for the site after its closure to be eligible for an exploitation permit. The closure of a research or exploitation centre must be promptly notified to the Mining Administration.
The holder of the mining rights is required to obtain a financial guarantee in an amount sufficient to carry out environmental rehabilitation.