D.C. Circuit Affirms FERC Finding of No Manipulation in ISO-NE Capacity Market Auction
  • Troutman Sanders LLP
  • USA
  • August 1 2018

On July 24, 2018, the D.C. Circuit Court of Appeals (“D.C. Circuit”) affirmed FERC’s 2015 and 2016 orders denying challenges to ISO New England’s


FERC Accepts and Sets for Hearing Cost-of-Service Compensation Agreement
  • Troutman Sanders LLP
  • USA
  • July 24 2018

On July 13, 2018, pursuant to section 205 of the Federal Power Act (“FPA”), FERC accepted and set for hearing a cost-of-service agreement between


MISO Proposes to Reinstate Prior Transmission Owner Network Upgrade Funding Mechanism
  • Troutman Sanders LLP
  • USA
  • July 17 2018

On July 5, 2018, the Midcontinent Independent System Operator, Inc. (“MISO”) proposed to restore provisions in its Open Access Transmission, Energy


FERC Finds ISO-NE’s Tariff May Not Adequately Address Fuel Security Concerns
  • Troutman Sanders LLP
  • USA
  • July 11 2018

On July 2, 2018, FERC denied ISO New England Inc.’s (“ISO-NE”) request for waiver of its Transmission, Markets, and Services Tariff (“Tariff”) and


FERC Conditionally Approves MISO Tariff Revisions Regarding Termination of GIAs
  • Troutman Sanders LLP
  • USA
  • June 26 2018

On June 21, 2018, FERC found that the Midcontinent Independent System Operator, Inc.’s (“MISO”) Open Access Transmission Tariff (“Tariff”) provisions


D.C. Circuit Upholds FERC’s Changes to PJM’s FTR and ARR Designs
  • Troutman Sanders LLP
  • USA
  • June 18 2018

On June 12, 2018, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) rejected challenges to FERC orders modifying PJM’s


Commissioner LaFleur Calculates Downstream GHG Impacts of Pipeline Project in Concurrence
  • Troutman Sanders LLP
  • USA
  • June 18 2018

On June 12, 2018, FERC Commissioner Cheryl LaFleur, through a concurrence in an order denying rehearing (“Rehearing Order”), announced that going


FERCDOJ Argue that Federal Power Act Does Not Preempt Illinois’ Zero Emission Credits Program
  • Troutman Sanders LLP
  • USA
  • June 5 2018

On May 29, 2018, the U.S. Department of Justice (“DOJ”) and FERC argued in a joint brief (“Joint Brief”) filed with the U.S. Court of Appeals for the


Complaint Asserts PJM Impermissibly Revised Generation Site Control Requirements
  • Troutman Sanders LLP
  • USA
  • May 29 2018

On May 22, 2018, GlidePath Power Solutions LLC (“GlidePath”) filed a complaint with FERC under Section 206 and 306 of the Federal Power Act alleging


FERC Clarifies CEII Rules
  • Troutman Sanders LLP
  • USA
  • May 23 2018

On May 17, 2018, FERC issued Order No. 833-A wherein it denied rehearing of Order No. 833 and granted, in part, Edison Electric Institute’s (“EEI”