In an order issued March 22, 2013, the Federal Energy Regulatory Commission ("FERC") addressed the Order No. 1000 compliance filings by PJM Interconnection, L.L.C. ("PJM"), and its transmission owning utilities ("PJM TOs").  In the order, the Commission found that PJM and the PJM TOs partially complied with Order No. 1000 requirements and required that further compliance filings be submitted within 120 days of the order, or by July 20, 2013.  Linked below is a memorandum summarizing the PJM order.