As you are all probably very aware, the CDM Regulations are set to change in April 2015. 

One interesting point is that there hasn't been any discussion about transition arrangements as of yet.  Those of us who were around when the 2007 Regulations became law will recall that there was a six month transition period before new and continuing projects were required to comply with the new Regulations.  However, the HSE has yet to confirm that the same arrangements will be put in place when the CDM Regulations 2015 become law next year.  There is therefore a concern that those tender documents being worked on now for projects starting on site next year could possibly be subject to the new Regulations.