Default, liability and remedies
Liability for defective design (after delivery)Do courts consider defective design to fall within the scope of poor workmanship for which the shipbuilder is liable under the warranty clause of the contract?
In the case of Aktiebolaget Gotaverken v Westminster Corporation of Monrovia and another (1971), the High Court held that a clause that imposed upon a repair shipyard warranty obligations in respect of ‘material used and work performed’ (and that was linked to another clause referring to ‘defects or deficiencies of material or workmanship’) was also apt to encompass the shipyard’s design errors. If there were design errors, there was no reason why these should not be characterised, and attract liability, as bad workmanship and, accordingly, be covered by the warranty provisions.
However, notwithstanding the above judgment, the parties often provide expressly that the builder’s warranty covers defects resulting from inadequate or erroneous design discovered in the warranty period in order to avoid any uncertainty on this issue.
The extent to which a buyer can recover its losses for defective design or poor workmanship, or both, under a warranty clause was considered in Star Polaris LLC v HHIC-Phil Inc (2016), which concerned the serious engine failure on a bulk carrier. The shipbuilding contract had excluded the builder’s liability for ‘any consequential or special losses’ and the court, upholding the decision of the arbitrators, considered that ‘consequential’ should be considered in its ‘cause-and-effect’ sense, rather than the traditional Hadley v Baxendale distinction direct and indirect losses. As a result, the buyer’s recovery was limited to the cost of repair and did not include its claims for loss of hire and diminution in value that were considered consequential to the repairs works provided for in the warranty provision.
Remedies for defectiveness (after delivery)Are there any remedies available to third parties against the shipbuilder for defectiveness?
Under English law, it is not straightforward for third parties to seek redress for damage suffered as a result of the defectiveness of the vessel.
In the absence of a contractual relationship, a third party’s ability to enforce the warranty rights under the shipbuilding contract is severely restricted. A third party may be entitled to enforce its terms, including the warranty clause, pursuant to the Contract (Rights of Third Parties) Act 1999 (the 1999 Act), although contracts usually contain provisions expressly excluding its application. For further details of the 1999 Act, see question 35. Taking an assignment of the buyer’s rights under the shipbuilding contract could be an alternative contractual route that third-party claimants may wish to explore, but this may in fact be impracticable as the shipbuilding contract, as is often the case, may prohibit any assignment or subject the same to the shipbuilder’s consent (see question 44).
Other than any contractual remedy, it may be open to a third party to establish the shipbuilder’s liability in tort, but this is not without its difficulties. First, unless there is no foreign element involved in the case, a claimant has to address the preliminary questions of jurisdiction and proper law (ie, respectively whether English courts have jurisdiction to hear the claim and which system of law should apply to determine the builder’s liability). Leaving aside the question of jurisdiction (which, depending on the circumstances, may be governed by the relevant European regulation, the applicable English statutory provisions or by common law), the applicable law for determining whether an actionable tort has been committed will generally be governed by either the Private International Law (Miscellaneous Provisions) Act 1995 (the 1995 Act), or by Regulation (EC) No. 864/2007 on the law applicable to non-contractual obligations (Rome II) where the damage occurred after 11 January 2009. Following Brexit, the UK government’s current intention is to incorporate Rome II, as well as Rome I, into UK domestic law, and if that occurs the UK will continue to apply the same rules when determining the law that governs the non-contractual obligations between the shipbuilder and the third party. Similarly, as with Rome 1 (see question 4), if the UK were to exit the EU without a deal (which at the time of writing remains a possibility), the UK government has confirmed that it would retain Rome II and, as this regulation does not depend on reciprocity, the rules to determine which law would apply in cross-border disputes concerning non-contractual obligations would remain the same in the UK.
To the extent that English law becomes relevant and the claimants wish to sue the shipbuilder under the tort of negligence, a host of difficult issues will arise as to the nature of the relationship between the claimants and the builder, as well as the nature of the loss suffered. Essentially, any claimant must demonstrate that its relationship with the shipbuilder attracted a legal duty of care and that the shipbuilder’s conduct breached that duty, and also that such conduct caused the claimant’s loss and the type of loss suffered was foreseeable as a result of the shipbuilder’s conduct. In Howmet Ltd v Economy Devices Ltd (2016), it was held that where a third party becomes aware of the defect before the damage occurs but continues to use the product, the shipbuilder would be able to escape liability.
The hurdles that a claimant has to overcome are significant, and even where a claimant can establish that the shipbuilder owed it a duty of care that the shipbuilder had then breached by building a defective vessel, the claimant might be unable to bring the type of loss suffered (for instance, pure economic loss as opposed to physical injury or property damage) within the types of losses to which the shipbuilder’s duty of care extends. Notably, English courts are reluctant to allow third-party claimants to recover pure economic losses by suing in negligence unless they can demonstrate the existence of a special relationship with the defendant or otherwise establish the defendant’s assumption of responsibility. A third party is, therefore, likely to face a considerable challenge to succeed in recovering losses by pursuing the shipbuilder in tort for negligence.
Brief mention should also be made of the statutory regime provided by the Consumer Protection Act 1987 (the 1987 Act). Under the 1987 Act, a ‘producer’ of a defective product is made liable without proof of fault for any damage arising from the defect. Ships are expressly included in the definition of products so there is accordingly scope for a claimant to bring a claim under the 1987 Act where it has suffered loss or injury because of the defective condition of a ship. A shipbuilder could, therefore, as a producer, face a claim where an accident can be proven to have resulted from a defect in construction. It was held by the European Court of Justice in Boston Scientific Medizintechnik v AOK Sachsen-Anhalt - Die Gesundheitskasse (2015) that it may not be necessary to show that the product itself is defective, if products belonging to the same group or forming part of the same production series have a potential defect, in which case it is possible to classify all the products in that group or series as defective. Although the case concerned pacemakers and defibrillators, it is not yet clear if this interpretation will be limited to medical cases.
However, while personal injury claims are largely unqualified by the 1987 Act, liability for property damage is significantly limited. First, the 1987 Act does not provide a remedy in respect of any damage to the product itself, even if caused by the defect. Second, it only applies to damage to property that is of a description ordinarily intended for private use, occupation or consumption and that is intended by the person suffering the loss to be mainly for its own use, occupation and consumption. As a result, most cases of damage to commercial ships and their cargo and any cargo damaged on the defective vessel fall outside the scope of the 1987 Act although, prima facie, damage caused by a defective vessel to private yachts and private property ashore would not be excluded.
Liquidated damages clausesIf the contract contains a liquidated damages clause or a penalty provision for late delivery or not meeting guaranteed performance criteria, must the agreed level of compensation represent a genuine link with the damage suffered? Can courts mitigate liquidated damages or penalties agreed in the contract, and for what reasons?
Until recently, the effectiveness of liquidated damages provisions was subject to the requirement that the agreed level of damages must represent a genuine pre-estimate of the losses arising from the relevant breach. In light of this test, where the level of compensation was found to be extravagant or unconscionable, the clause would be treated as a penalty and would therefore be legally unenforceable. In recent years, case law indicated a departure from simply considering whether the provision represents a genuine pre-estimate of loss, with courts adopting a broader test involving an examination of whether it was unconscionable with a predominant purpose of deterrence, but not finding a provision to be an unlawful penalty if there was commercial justification for it.
The test has, however, been definitively clarified by the Supreme Court in 2015 in the conjoined appeals of Cavendish Square Holdings BV v Talal El Makdessi and ParkingEye Limited v Beavis (2015). In essence, whether a contractual provision is a penalty is a question of interpretation, with the real question being whether the clause is penal or punitive in nature. A penalty clause can only exist where a secondary obligation (eg, to pay liquidated damages) is imposed following a breach of a primary obligation owed by one party to the other (eg, a failure to meet performance guarantees) and is to be distinguished from a conditional primary obligation, which depends on events that are not breaches of contract. It is therefore potentially possible to circumvent the penalty rule with careful drafting, as was the case in Holyoake and another v Candy and others (2017), where the penalty arose under a primary obligation, namely the option to repay a loan early. Where a provision in substance, rather than in form, imposes a secondary liability for breach of a primary obligation that is out of all proportion to any legitimate interest of the innocent party in the performance of the primary obligation or is exorbitant, extravagant or unconscionable in comparison with the value of that legitimate interest it will be considered penal. The onus lies on the party alleging that a clause is a penalty to show this. As the penalty rule is an interference with freedom of contract, the courts will not lightly conclude that a term in a contract negotiated by properly advised parties of comparable bargaining power is a penalty. In GPP Big Field LLP v Solar EPC Solutions SL (formerly Prosolia Siglio XXI) (2018), a case concerning the construction of five solar power generation plants, the liquidated damages clause was upheld notwithstanding that the amounts payable were referred to as a penalty and remained the same across all five contracts, even though the outputs and revenues from the projects differed. Further, following the insolvency of the contractor and termination of the contract, liquidated damages were still payable until the works were completed by a replacement contractor. Earlier case law considering whether specific clauses are penal will still be relevant, as the Supreme Court considered it impossible to lay down abstract rules as to what may or may not constitute ‘extravagant’ or ‘unconscionable’. These include the High Court cases of Azimut-Benetti SpA v Healey (2011) (concerning a yacht builder’s claim for an amount equal to 20 per cent of the contract price by way of liquidated damages on its termination of the yacht construction contract for the buyer’s late payment of an instalment) and North Shore Ventures Ltd v Anstead Holdings Inc (2010) (concerning the uplift of the interest rate payable by the borrower under a loan agreement on any payment or repayment default (from 15 per cent to 20 per cent)).
There is also authority to indicate that the courts will interpret liquidated damages clauses to prevent their application where the relevant underlying breach of contract is relatively minor. This de minimis approach was adopted by the Court of Appeal in Cenargo Ltd v Izar Construcciones Navales SA (2002), which concerned a provision for payment of liquidated damages for reductions in the vehicle-carrying capacity of ferry newbuildings. The cost of the modifications, at around US$11,000, was substantially less than the liquidated damages claim under the contract of around US$750,000. While this case provides that where the contractual provision would result in a substantial liability in liquidated damages, but the defect can be remedied for a significantly lower amount, that party’s liability should be limited to the lesser sum, this judgment is considered to be controversial as it has been felt to run counter to the whole premise of a liquidated damages clause being to reflect the contractual bargain between the parties for a specific breach of contract. For example, more recently, in the first instance decision in MSC Mediterranean Shipping Company SA v Cottonex Anstalt (2015) and approved obiter by the Court of Appeal (2016), demurrage, which was payable by a charterer to a shipowner for failure to load or unload goods on time and recognised as a payment of liquidated damages, did not require the innocent party to prove its actual loss or mitigate that loss when it fell due.
Where a contract provides for a penalty fee that is not judged to be penal but makes no reference to damages or liquidated damages in the relevant clause and the fee is not intended as a substitute for common law damages, the Privy Court found that the fee would not form part of the calculation made by the court when determining what damages could be recovered (see Brown’s Bay Resort v Pozzoni (2016)).
Preclusion from claiming higher actual damagesIf the building contract contains a liquidated damages provision, for example, for late delivery, is the buyer then precluded from claiming proven higher damages?
If the loss arising from the breach exceeds the level of the liquidated damages, it is clear that the liquidated damages provision limits the liability of the party in breach to the agreed amount under the clause. The claimant will need to establish an alternative or additional breach of contract to sue for its actual loss in such a case. Where a builder fails to deliver a vessel by the contractual delivery date, the buyer’s remedy is usually (subject to the terms of the particular contract) limited to the liquidated damages provisions of the contract dealing with delay in delivery. However, where the liquidated damages clause is successfully challenged as constituting an unlawful penalty and therefore unenforceable, both parties are disabled from invoking it. In such a case, the innocent party is entitled to sue for its actual losses, subject to the usual rules of remoteness of damage and causation.
Force majeureAre the parties free to design the force majeure clause of the contract?
Parties are free to design the force majeure clause and it is important that due consideration is given to doing so because English law, unlike some civil law jurisdictions, does not recognise any general doctrine of force majeure. Accordingly, the parties must specify the events that will constitute force majeure and typically include events such as acts of God; war or other hostilities; blockade; civil war; strikes, lockouts or other labour disturbances; labour shortage; flood, typhoons, hurricanes, storms or other weather conditions not included in normal planning; earthquakes; tidal waves; landslides; fires; and explosions. The parties must also specify the effect of the occurrence of such an event. The contract usually sets strict time limits within which the commencement and ending of the event must be notified, and failure to do so can be fatal to successfully claiming force majeure (see by way of recent example GPP Big Field LLP v Solar EPC Solutions SL (formerly Prosolia Siglio XXI) (2018)). The scope of the force majeure clause will affect the extent to which the builder is entitled to an extension of time for completion of the vessel and the remedies available to the buyer where the builder fails to meet the delivery date (as discussed in questions 26, 36 and 37). Two recent cases (Seadrill Ghana Operations Ltd v Tullow Ghana Limited (2018) and Classic Maritime Inc v Limbungan SDN BHD & Anor (2018)) make it clear that where a party seeks to rely on a force majeure event, it must show causation and establish that it would have performed the contract but for the force majeure event.
Umbrella insuranceIs certain ‘umbrella’ insurance available in the market covering the builder and all subcontractors of a particular project for the builder’s risks?
The Institute of London Underwriters’ Builders’ Risks Clauses dating from 1988 (the 1988 Clauses) are recommended as the minimum insurance in BIMCO’s Newbuildcon and widely used to cover the risks of physical loss of and damage to the vessel and her components during the period of construction. Generally, the cover incepts at the stage of keel laying (although the parties may agree a different stage of construction) and lapses upon delivery of the vessel to the buyer. Insurance is on an all-risks basis (subject to certain limitations) in respect of loss or damage to the vessel or her components, including repair or replacement costs of parts condemned owing to latent defects discovered within the period of the insurance. It is usual for builders’ risks policies to identify the insured parties in broad terms in order to include, in addition to the builder as the principal assured, other parties involved with the project, such as the builder’s subcontractors and suppliers.
The more recent London Marine Construction All Risks (MarCAR) 2007 clauses were released in 2007 (the MarCAR 2007 Clauses) to suit a wider range of projects (including conversion, repair, lengthening or other similar work, as well as the construction of LNG carriers and high-value cruise vessels) than the 1988 Clauses and to address certain shortcomings perceived in those clauses. However, insurance written on the terms of the 1988 Clauses remains the norm.
Coverage for the construction and modification of vessels and installations employed in the offshore oil and gas sector is usually provided on the Offshore Construction Project Policy (WELCAR 2001) terms. WELCAR 2001 provides general all risks coverage throughout the construction process, from initial procurement to start-up. The Lloyds’ Joint Rig Committee is currently considering the WELCAR wording after WELCAR 2011, while produced, was not published.
Aside from WELCAR, it is not uncommon for parties to opt for CAR (contractors all risks) or EAR (erection all risks) coverage. The former is designed to cover all loss or damage to insured property (such as permanent property resulting from the works, construction equipment, worksite property and removal of debris) and liability towards third parties for death, bodily injury and damage to property, while the latter predominantly provides cover for risks associated with the erection, installation and commissioning of equipment, machinery, plant and structures. Although both of these policies are generally used for onshore construction and infrastructure projects, subject to the insurance arrangements of the parties, they may also be suitable for some shipbuilding and offshore construction projects.
Disagreement on modificationsWill courts or arbitration tribunals in your jurisdiction be prepared to set terms if the parties are unable to reach agreement on alteration to key terms of the contract or a modification to the specification?
Where the contract provides for any dispute to be submitted to the High Court, the court will not normally be prepared to set terms for the parties if they cannot agree them themselves, although it may be willing to determine what would be a reasonable adjustment to the contract price or a reasonable delivery date. If, however, arbitration is the chosen means for dispute resolution, the position may be different. Marine construction contracts governed by English law often include a term that, when making its award, the tribunal may include a finding as to any extension of the delivery date (which, for instance, allows the builder to seek extra time where the arbitration itself has caused delay to completion of the vessel). However, that is usually as far as the term goes - there is typically no provision for what criteria are to be applied by the tribunal in exercising this discretion. Further, if the parties wish the tribunal to determine any reasonable adjustments to other terms of the contract, such as the contract price, the contract should expressly confer that power on the tribunal. Under the Arbitration Act 1996, the parties are free to agree on the powers exercisable by a tribunal as regards remedies. Unless otherwise agreed by the parties (or by reference to the rules of the applicable arbitral institution), the tribunal has wide powers, including ordering payment of a sum of money in any currency, making a declaration as to any matter to be determined in the proceedings, ordering a party to do or to refrain from doing anything, ordering specific performance of the contract and ordering rectification, setting aside or cancellation of a deed or other document. However, neither the arbitral tribunal nor the court can otherwise amend the terms of the contract. It is also important to consider where such a non-damages remedy is sought and the other party subsequently does not act in accordance with the arbitral award, whether such a remedy can actually be enforced in the jurisdiction where the award would need to be enforced.
It is not unusual to encounter provisions in shipbuilding contracts requiring further negotiation or agreement between the parties. The general position under English law is that true agreements to negotiate or agreements to agree are unenforceable (see, for example, Walford v Miles (1992)). In many cases where, therefore, parties fail to reach agreement on the contract price, delivery date or other key terms, neither the court nor an arbitration tribunal will usually be prepared to set such terms for them. However, that is not always the case, and often the court or arbitration tribunal will strive to uphold the contract that the parties have entered into by implying a term into the contract to make it enforceable. In Teekay Tankers Limited v STX Offshore and Shipping Company (2017), where the parties entered into an option agreement for three options for the construction of up to four vessels, each with the delivery dates to be mutually agreed and with the builder using best efforts to have a delivery in certain specified windows, the parties were unable to reach agreement as to the delivery dates for the first and second options when exercised, but the court would not imply the terms that the buyers said should be implied into the option agreement because it took the view that such terms were at odds with the parties’ scheme as set out in the option agreement. However, whether this approach is applicable in all cases will depend upon the construction of the contract.
The conclusion of a letter of intent is a typical first stage in most newbuilding projects, the main purpose of which is usually to secure the slot in the shipyard’s building schedule for a period during which the parties will negotiate the contract and specification of the vessel, and also to set out certain key terms, such as delivery date, payment terms and perhaps options on further vessels. As a matter of English law, unless (unusually) the letter of intent expressly states that it creates a legally binding agreement, its enforceability will be a matter of construction, although that wording alone may not be sufficient to result in an enforceable letter of intent. Where the terms included contain provisions as to consideration and governing law and jurisdiction, the requisite intention to create a contractual relationship is likely to be found. However, even if such an intention is present, the letter of intent will still not be enforceable if, on its true construction, it provides no more than an agreement to agree or an agreement to negotiate. However, recent case law has shown that, depending on the construction of the terms of the particular contract, it is possible for an agreement to agree or to negotiate to be enforceable, although recent reported cases demonstrate how nuanced the position can be. Recently, in Arcadis Consulting (UK) Ltd v AMEC (BSC) Ltd (2018), the Court of Appeal found that where a party started work on a project following receipt of a letter of instruction that was sufficient to amount to acceptance, even though negotiations were ongoing and never finalised. The letter of instruction stood as the contract between the parties and incorporated the terms and conditions that the parties were already working under on another contract, even though the parties continued to negotiate the terms and conditions as part of the failed negotiations.
Acceptance of the vesselDoes the buyer’s signature of a protocol of delivery and acceptance, stating that the buyer’s acceptance of the vessel shall be final and binding so far as conformity of the vessel to the contract and specifications is concerned, preclude a subsequent claim for breach of performance warranties or for defects latent at the time of delivery?
The principal purpose of the protocol of delivery and acceptance is to record the time and date that title and risk pass to the buyer. It is also typically required to enable the builder to obtain the delivery instalment of the contract price.
The effect of the protocol of delivery and acceptance was reviewed by the High Court in the case of Riva Bella SA v Tamsen Yachts GmbH (2011), which concerned the resale of a newbuild yacht. It was held that in certain circumstances (for instance, where the contract itself expressly provides), by accepting the vessel and by signing a protocol of delivery and acceptance, the buyer may be precluded from rejecting the vessel (at least with regard to patent defects) and prevented from claiming damages against the seller, and may instead be confined to the remedies arising under the contractual warranties. The court held, however, that, in the ordinary course, acceptance will not prevent a claim for damages (this was recently confirmed in Saga Cruises BDF Ltd and another v Fincantieri SPA (2016), which concerned a contract for dry docking, repair and refurbishment of a cruise ship). This is also clear from the judgment of the Court of Appeal in the Cenargo case referred to in question 26, where acceptance of a vessel from the builder was held not to preclude the buyer from asserting at delivery or thereafter any claim for liquidated damages for breach of any performance warranty.
It is relatively unusual to find a protocol of acceptance stating that ‘buyer’s acceptance of the vessel is final and binding so far as conformity of the vessel to the contract and specifications are concerned’. Most protocols confine the statement to delivery ‘in accordance with’ or ‘pursuant to’ the contract. However, such a term is frequently encountered as part of the provisions regarding sea trials in the shipbuilding contract itself. In China Shipbuilding Corporation v Nippon Yusen Kabukishi Kaisha and another (2000), it was held that, in the context of the buyer’s express or deemed acceptance of the vessel following trials (ie, in the sense of confirmation of approval of the vessel as distinct from taking possession following formal tender of delivery), a provision that acceptance ‘shall be final and binding so far as conformity of the vessel to this contract and the specifications is concerned’ was limited. Such a term was found merely to prevent the buyer from refusing the later delivery of the vessel when she was tendered; it did not preclude the buyer from asserting after delivery the existence of specific defects whether previously notified to the builder or latent at the time of delivery.
However, the terms of a certificate of acceptance may be such as to constitute clear and unequivocal agreement by the buyer that the goods conform on delivery with the required contractual condition, thereby preventing the buyer from later claiming otherwise. The construction of such a certificate was central to the Court of Appeal’s decision in Olympic Airlines SA (in special liquidation) v ACG Acquisition XX LLC (2013) in the context of delivery of an aircraft under an aircraft lease (although the terms of that acceptance certificate exceeded those usually encountered in a typical protocol of delivery and acceptance used at delivery in a shipbuilding project) and to the High Court’s decision in ABN Amro Commercial Finance plc v McGinn (2014) in the context of a conclusive evidence certificate given by the lender in relation to a claim under an indemnity.
Liens and encumbrancesCan suppliers or subcontractors of the shipbuilder exercise a lien over the vessel or work or equipment ready to be incorporated in the vessel for any unpaid invoices? Is there an implied term or statutory provision that at the time of delivery the vessel shall be free from all liens, charges and encumbrances?
Under English law, a lien is a right over the property of another arising by operation of law, independently of any agreement. There are various categories of lien but the most relevant here would be a legal lien (also known as a possessory or common law lien), which gives the lienor a right to retain the property until the owner has settled some debt owed to the lienor. There are various subcategories of common law liens. However, if the equipment is already in the possession of the builder, ready to be incorporated into the vessel, the essential element of the lien (ie, possession by the lienor) will be missing.
In any event, it is usual practice for the builder to issue a written declaration at delivery of the vessel’s freedom from encumbrances and the bill of sale typically provided at delivery will usually contain a similar express covenant. Such a warranty will (unless expressly excluded) also be implied by section 12(2)(a) of the Sale of Goods Act 1979.
Reservation of title in materials and equipmentDoes a reservation of title by a subcontractor or supplier of materials and equipment survive affixing to or incorporation in the vessel under construction?
It is common for suppliers to incorporate into their contracts retention or reservation of title clauses. These usually stipulate that the supplier retains the property in the goods until such time as full payment has been made. The validity of these clauses was established in the case of Aluminium Industrie Vaasen BV v Romalpa Aluminium Ltd (1976), but while the practical effects of these clauses seem well understood, the legal issues arising are often less so.
It is important to distinguish the simple retention of title clause from a security agreement. The latter (where the transaction involves companies) may well require registration as a registrable charge under section 859A of the Companies Act 2006. A simple retention of title clause will not have this effect and is not a charge because property in the goods is retained by the original supplier and never passes to the buyer. As the buyer was never the owner, it would never be able to grant any interest in the goods to the seller by way of security. However, retention of title clauses vary considerably and a sophisticated clause may well be found to constitute a charge, especially where it grants back to the seller any beneficial or equitable interest. In company law, there is a regime for the registration of charges that serves as notice to any subsequent buyer or subsequent chargee of the existence of the charge. The failure of a supplier to register a registrable charge means that any such subsequent chargeholder or buyer can ignore the claims of the original supplier who will be left with its claims against the buyer under the contract. This would clearly be disastrous for the original supplier if the buyer became insolvent. It is, therefore, important to ensure that any such clause is carefully reviewed.
Where material has been delivered by the supplier to the shipbuilder pursuant to a contract containing reservation of title provisions, to the extent that the material remains held in stock and available, the clause should be effective to ensure the property remains vested in the supplier. However, where the goods have been incorporated in, or used as material for, other goods, detailed analysis of the resulting product will be required to establish ownership. It cannot be assumed that if a supplier is unable to identify its particular goods, its retention of title clause will be defeated. In the first instance, it will be necessary to establish the extent to which the original goods supplied have retained their original identity. Where the identity of the original goods has been lost, the buyer is likely to have acquired title. If, however, the original goods have been mixed with goods owned by a third party, a supplier’s retention of title claim will not necessarily be defeated, particularly if such goods retain their original identity or can be extracted from the manufacturing process.
There is authority for the assumption that the newly manufactured goods are owned by the buyer of the original goods (ie, the shipbuilder) but that the clause itself may then provide evidence of a charge created in favour of the supplier (to which the issues raised above are then relevant). Depending again on the precise terms of the contract between them, notwithstanding any retention of title provision, the shipbuilder, as a party that has agreed to buy goods and therefore a buyer in possession after sale, is permitted under section 25 of the Sale of Goods Act 1979 to sell the goods and pass good title. The supplier is left with a claim for damages.
Third-party creditors’ securityAssuming title to the vessel under construction vests with the builder, can third-party creditors of the builder obtain a security attachment or enforcement lien over the vessel or equipment to be incorporated in the vessel to secure their claim against the builder?
The availability of any such right of a third-party creditor to obtain a security attachment or lien over the vessel or equipment will depend upon the lex situs, that is, the law of the place of construction (see generally question 13).
As the vast majority of shipbuilding contracts governed by English law provide for title to the vessel to pass to the buyer on delivery, at that point in time, the builder is required to issue a written declaration that the vessel is free from, among other things, charges and liens (see question 32) and will want to ensure that it can make the declaration required.
Subcontractor’s and manufacturer’s warrantiesCan a subcontractor’s or manufacturer’s warranty be assigned to the buyer? Does legislation entitle the buyer to make a direct claim under the subcontractor’s or manufacturer’s warranty?
Whether such a warranty can be assigned will depend on the terms of the relevant contract. Under English law, in the absence of an express prohibition in the contract, the benefits (but not the burdens) of a contract can generally be assigned by either party to a third party (see question 44).
Where the assignment is made in writing, is signed by the assignor, is in absolute terms (and not by way of charge only) and a written notice of the same is given to the contractual counterpart, it will satisfy section 136 of the Law of Property Act 1925 and constitute a legal assignment. As a result, the assignee assumes the rights of the assignor under the contract and may enforce such rights itself directly against the other contracting party. The notice of assignment must be given before the assignee can exercise its contractual rights, such as giving notice to terminate the contract, as was confirmed in the recent case of General Nutrition Investment Company v Holland and Barrett International Ltd (2017). Where the statutory formalities have not been met, the assignee may still be able to enforce the assignment in equity by requiring the assignor to sue on its behalf.
Under the Contract (Rights of Third Parties) Act 1999, it is now possible in certain circumstances for contractual rights to be enforced directly by a third party provided that the contract expressly provides that the third party may do so or a relevant term ‘purports to confer a benefit upon him’ and, on the proper construction of the contract, it is clear that the parties intended that such third party should be entitled to enforce it. The third party must ‘be expressly identified in the contract by name, as a member of a class or as answering a particular description but need not be in existence when the contract is entered into’. Such a third party is entitled to the same remedies as would have been available to it in an action for a breach of contract if it had been an original party. However, the contractual defences available to the original parties are preserved in relation to the third party and it is open to the original parties to set conditions on a third party’s rights to enforce any term. This Act substantially changed contractual doctrine as to third-party rights and, in light of its significant implications, is routinely excluded in manufacturers’ warranties.
Default of the builderWhere a builder defaults in the performance of the contract, is there a legal requirement to put the builder in default by sending an official notice before the buyer’s remedies begin to accrue? What remedies will be open to the buyer?
It is usual for the parties to agree that certain defined events of default will entitle the buyer to terminate the contract by exercising express rights in the contract to this effect. Most shipbuilding contracts define delay in delivery, technical deficiencies in the vessel, insolvency events and total loss as such events entitling termination.
It is important to ensure that the party seeking to terminate the contract complies with any contractual mechanism or procedure for terminating, including the service of notices of default. However, as illustrated in the first instance decision of Obrascon Huarte Lain SA v Attorney General of Gibraltar (2014), and not challenged on appeal, strict compliance with such a procedure may not be essential, an approach that the judge considered ‘accords with commercial common sense’, although a party terminating a contract will certainly not want to have to rely on this decision. However, in a recent arbitration award (London Arbitration 2/19), the tribunal said that the builder was obligated to give notice of any delay for which it claimed an extension of time to the delivery date because certainty was of great importance in commercial contracts and it was essential that both parties knew when the right to cancel could be exercised.
When a party wishes to exercise its right to terminate at common law, it will not be necessary for that party to comply with the express contractual termination provisions, including any notice requirements, unless the express wording of the termination provision states that it applies to termination at common law. The case of Vinergy International (PVT) Ltd v Richmond Mercantile Ltd FZC (2016) confirmed that such a term cannot be implied into the termination provision of a contract.
If the buyer exercises a right to terminate, the builder will normally have to refund the instalments paid up to that point, together with interest at an agreed rate. Where title passes on delivery, the builder’s obligation to refund the pre-delivery instalments is normally secured by a refund guarantee, the provision of which is usually a condition precedent to the effectiveness of the contract.
Even if the buyer is refunded its advance instalments and interest, the buyer may still incur substantial losses as a result of the termination. These losses may be categorised as either loss of bargain (usually expressed as the difference between the contract price and the market price for an equivalent newbuilding) or reliance loss (wasted expenditure as a result of the termination of the contract). These losses are not normally recoverable from the builder, as shipbuilding contracts invariably limit the builder’s obligations on termination by the buyer to repayment of the advance instalments with interest.
Where the victim of a breach of contract prefers performance of the contract rather than its termination, in theory it may be possible for it to obtain an order of specific performance from the High Court or arbitration tribunal. This is an order directed to the party in breach to fulfil its contractual obligations. However, it is a discretionary remedy and seldom granted: for example, an order for specific performance will not be made where an award of damages would adequately compensate the victim. Also, in a shipbuilding context, the courts have refused to order specific performance to ensure completion and delivery of a vessel, due to the difficulty of ensuring adequate supervision of a complex construction project (although the position may be otherwise where the vessel is actually complete, as the remedy has been granted in the context of sales of second-hand vessels). The case of Liberty Mercian v Cuddy Civil Engineering Ltd and another (2013) indicates that the mere fact that some level of supervision is required does not of itself prevent a court from granting an order for specific performance.
It may, however, be possible to characterise the builder’s conduct as being a repudiatory breach of contract, which is essentially where the breach is either in relation to a term that is correctly categorised as a contractual condition, or is serious enough to deprive a party of substantially the whole benefit it intended to obtain from the contract. If so, the breach gives that party a common law right to treat the contract as discharged and to recover damages for loss of bargain. This position was reaffirmed in the important case Stocznia Gdynia SA v Gearbulk Holdings Ltd (2009). The Court of Appeal in the Gearbulk case held that the particular contractual provision (regarding delay in delivery) did not exclude a right to terminate under common law and also did not exclude the claimant’s rights to recover losses in the usual way, so the buyer could claim damages for loss of bargain. Furthermore, the exercise of its contractual rights to recover the instalments did not prejudice the claimant’s ability to claim damages for the builder’s repudiatory breach because it could recover those instalments under the doctrine of total failure of consideration, which was distinct from any right to recover damages for loss of bargain. The Gearbulk case provides an example of a failure to exclude the buyer’s common law rights. However, where common law rights are not excluded but a party terminates in accordance with an express contractual right only, and that right does not amount to a breach of contract, the innocent party will subsequently be precluded from claiming common law remedies for breach because they had not terminated for a repudiatory breach of contract (actual or anticipatory). In the recent decision of Phones 4U Limited (in administration) v EE Limited (2018), the innocent party lost the right to claim loss of bargain damages because the basis for termination set out in the notice of termination was the appointment of administrators only. This case illustrates that it is crucial that a party should carefully considers its legal options, and obtain legal advice before serving notice of termination.
Remedies for protracted non-performanceAre there any remedies available to the shipowner in the event of protracted failure to construct or continue construction by the shipbuilder apart from the contractual provisions?
Depending on the circumstances of the case and the terms of the contract, it may be open to the shipowner, in addition to any contractual remedies, to treat a protracted failure to construct or to continue construction as a repudiatory breach of contract by the builder entitling the shipowner to accept the repudiation (so as to bring the shipbuilding contract to an end) and to claim damages in respect of losses caused by the breach. A shipowner may have to wait until it is impossible for the builder to meet the delivery date before it can exercise such a right and cancel the contract. If beforehand the builder evinces an intention not to perform its obligations in some essential respect, the builder’s actions may amount to renunciation of the contract, allowing the shipowner to accept the breach and sue for damages before performance is required under the contract. In Teekay Tankers Limited v STX Offshore and Shipping Company (2017) referred to in question 30, the judge considered obiter that it was clear from the statements made by the builder regarding the provision of refund guarantees that the builder did not intend to fulfil its obligations and the shipowner would therefore have been entitled to terminate on that basis.
Where the contract sets out the delivery date but does not already make time of the essence, the shipowner’s position in the event of protracted failure to construct or continue construction by the shipbuilder may require, or at least be strengthened by, the serving of a notice making time of the essence, as long as it gives the shipbuilder a reasonable time to complete construction. Such a notice should be sent as soon as the breach arises, but the shipowner does not need to wait until there has been unreasonable delay before sending it (see Behzadi v Shaftesbury Hotels (1992)).
Builder’s insolvencyWould a buyer’s contractual right to terminate for the builder’s insolvency be enforceable in your jurisdiction?
Clauses granting the buyer the right to terminate the contract if the builder becomes insolvent (or commits any other type of defined ‘financial default’) are not uncommon in English law shipbuilding contracts (such a provision appears in the Newbuildcon form, although not in the SAJ form). In Fibria Celulose S/A v Pan Ocean Co Ltd and another (2014), Fibria contended that it was entitled to cancel a contract of affreightment with the South Korean shipping company in accordance with the terms of the contract on the basis of it being subject to an insolvency process. The company was subject to a rehabilitation process in Korea, which was regarded as being broadly comparable to an English administration coupled with a scheme of arrangement or company voluntary arrangement. The company disputed this entitlement and contended that the English court had jurisdiction under the Cross-Border Insolvency Regulations 2006 (SI 2006/1030) to make an order restraining Fibria from relying on such provision. The court held that on a proper construction of the Regulations, the English court had no power to order a stay in relation to Fibria’s entitlement to serve such a termination notice under the contract and nor could it make an order restraining it from doing so.
The judge noted that in some jurisdictions, a clause that allows a party to a contract to terminate the contract by reason of the insolvency of the counterparty is called an ‘ipso facto’ clause. While in some jurisdictions such clauses are automatically invalid or the court has power to stay the exercise of rights under such clauses, there was no dispute in this case as to the efficacy of such a provision under English law. Indeed, the judge remarked that it was accepted that those provisions are valid in English law. In particular, it was accepted that the rule of insolvency law, known as the anti-deprivation rule, does not strike down such provisions. (The anti-deprivation rule can be briefly summarised as that which on insolvency prevents parties from depriving the insolvent company of property that would otherwise be available for creditors.)
Judicial proceedings or arbitrationWhat institution will most commonly be agreed on by the parties to decide disputes?
The parties commonly choose which arbitration institution or country’s courts will have jurisdiction over any disputes that arise under or in connection with the contract. Such clauses commonly override the basic principle that a defendant should be sued in his or her country of domicile. Arbitration is the preferred mechanism to resolve disputes arising under shipbuilding contracts. References are usually to a sole arbitrator or to a tribunal of three arbitrators in accordance with the rules of an arbitration institution, such as the London Maritime Arbitrators’ Association (LMAA) and its Terms (the current version is the LMAA Terms (2017)) and the provisions of the Arbitration Act 1996. Where judicial proceedings are selected, disputes are typically agreed to be submitted to the Commercial Court or the Technology and Construction Court in London, both of which (as of June 2017) form part of the Business and Property Courts of England and Wales.
Arbitrations are often preferred because they are typically confidential and awards are generally more easily enforced around the world than English court judgments, owing to the Convention on the Recognition and Enforcement of Foreign Arbitral Awards, also known as the New York Convention, and this will remain the case, notwithstanding Brexit. At present, enforcement in EU member states of English court judgments is governed by the Recast Brussels Regulation. However, there is some uncertainty as to how such judgments will be enforced within the EU following Brexit and certainly in the event of the UK exiting the EU without a deal (which at the time of writing remains a possibility), as the UK government has indicated that it intends to repeal these rules. If this is the case, it is likely that it will be easier to enforce an arbitral award abroad than an English court judgment.
It is possible to challenge an arbitrator’s award for lack of substantive jurisdiction, for serious irregularity or on a question of law, and as a result the dispute may end up before the courts. Where there are related contracts, for example, the shipbuilding contract and the refund guarantee, it is not uncommon to find that disputes arising under the former will be dealt with by arbitration, while the latter is subject to separate court proceedings.
Buyer’s right to complete constructionWould a buyer’s contractual right to take possession of the vessel under construction and continue construction survive the bankruptcy or moratorium of creditors of the builder?
While a buyer’s contractual right to take possession of the vessel under construction and continue construction would survive the bankruptcy or moratorium of the creditors of the builder under English law, this is an issue that would be determined by the lex situs, that is, the law of the place of construction, which is not normally England or Wales. In such circumstances, appropriate legal advice should be sought from local counsel to clarify the position.
ADR/mediationIn your jurisdiction, do parties tend to incorporate an ADR clause in shipbuilding contracts?
Of the standard forms of shipbuilding contract typically encountered (see question 43), only BIMCO’s Newbuildcon contains extensive, formal ADR provisions. In particular, this standard form provides a detailed mediation clause that permits the parties to refer any dispute arising out of the contract to mediation even if they have previously agreed to submit such dispute to arbitration and even if arbitration has already been commenced (in which case the arbitration proceedings are to continue during the conduct of the mediation and the tribunal has the power to adjust the arbitration timetable to take the mediation into account). Aside from BIMCO’s Newbuildcon, it still remains relatively unusual to see provision for formal ADR procedures such as mediation, early neutral evaluation or the like provided for in shipbuilding contracts, although it may be agreed that the parties are to convene a meeting between senior management to try to resolve any dispute before arbitration or court proceedings are commenced. Where litigation is the agreed mode of dispute resolution, the English High Court encourages and has the power to order parties to engage in ADR procedures before or after formal proceedings are commenced and may stay the proceedings to allow for this to happen.
It is not uncommon for maritime construction contracts, particularly those in the offshore sector, to provide for an escalation procedure in an attempt to settle disputes through senior management before commencing formal arbitration or litigation. It was generally considered that where such a ‘tiered dispute resolution clause’ was included in a contract, any requirement for the parties to hold such discussions before the dispute was referred to formal dispute resolution was likely to be held unenforceable as it amounted to an agreement to agree (see question 30). However, in the case of Emirates Trading Agency LLC v Prime Mineral Exports Private Limited (2014) the High Court held that, provided such a term is not incomplete and not uncertain, a requirement to hold ‘friendly discussions’, such as appears in the CMAC form, may well not be a mere agreement to negotiate and could, depending on the facts, be enforceable. Stipulating that those discussions are conducted in good faith generally does not add to the obligations on the parties and can instead lead to a dispute as to whether a duty of good faith has been imposed and what this amounts to.
Default of the buyerWhere the buyer defaults in the performance of the contract, what remedies will be available to the builder? What are the consequences of the builder’s cancellation of the contract?
As with default by the builder (see question 36), it is usual for the parties to agree that certain defined events will entitle the builder to terminate the contract by exercising express rights in the contract to this effect in the event of default by the buyer. Most shipbuilding contracts define the buyer’s failure to make timely payment of the instalments of the contract price or to take delivery of the vessel when it is tendered for delivery as events entitling termination, but depending on the financial standing of the buyer, such a clause could also include insolvency events.
Some shipbuilding contracts provide that the builder must give notice of default to the buyer, specifying a period during which the buyer can remedy the default, as a condition precedent to the builder’s right to terminate the contract, but it is common for the builder to have the automatic right to terminate the contract upon the buyer’s breach without notice of default.
The shipbuilding contract will set out the consequences of the buyer’s default. Where the buyer fails to pay any instalments, the shipbuilding contract will commonly provide that the buyer is obliged to pay an agreed rate of interest from the date of the default until payment, including interest, is made in full. It may also require the buyer to pay all charges and expenses incurred by the builder as a consequence of the default. Such provisions also commonly provide that the delivery date will automatically be extended for the period of such default regardless of whether the construction of the vessel has been delayed as a result, although they are often amended to limit the extension to the period of time when the builder’s construction programme is delayed. If the default continues for more than a set number of days, the builder will normally have the option to terminate the shipbuilding contract by giving notice to the buyer.
By cancelling the shipbuilding contract, the builder has brought an end to its obligation to construct the vessel and the buyer’s obligation to purchase the vessel. On cancellation, the builder is normally entitled to retain the instalments of the contract price already paid by the buyer. The builder must, however, give credit for such sums in the ‘final accounting’. As to instalments that are due but unpaid, termination of a contract of sale can prevent the recovery of any unpaid instalments from the buyer on the basis that the price is no longer payable (see Dies v British and International Mining and Finance Corporation Ltd (1939)). In the context of shipbuilding contracts, however, unless the builder has done nothing in the performance of the contract such that there has been a total failure of consideration (see Hyundai Heavy Industries and Stocznia Gdanska, both referred to in question 5), the buyer cannot contend that the unpaid instalments are no longer due and instalments that have therefore accrued due, but remain unpaid by the buyer at the time of builder’s termination, are recoverable by the builder. As to future payments, in the absence of express wording to the contrary, the builder’s rescission of the shipbuilding contract will prevent the builder from seeking to recover any future instalments of the contract price. Shipbuilding contracts also commonly provide that on rescission by the builder, title in the buyer’s supplies will transfer to the builder. However, this is normally limited to those buyer’s supplies that have been installed or have been utilised on board the vessel.
Following termination of the shipbuilding contract, the builder will normally be entitled to sell the vessel, either in its existing condition, or to continue with the construction of the vessel and sell it once it has been completed. Shipbuilding contracts usually expressly provide for the application of the proceeds realised upon sale for each such scenario. In Stocznia Gdanska, the House of Lords held that the vessel did not need to be completed in accordance with the original specification in order to amount to a sale of the vessel under the relevant default clause. The appropriate course of action will normally be determined by the stage that construction has reached, together with the state of the newbuilding market at the relevant time. While shipbuilding contracts generally allow the sale to take place publicly or privately, the builder is normally subject to either an implied or express duty to act in good faith to prevent the sale of the vessel at an undervalue. Once the vessel has been sold, a final accounting will take place and take into account the original contract price or the builder’s costs of construction or any anticipated lost profit of the builder (depending on the contract terms and whether the vessel was sold in a complete or incomplete state), and the instalments paid by the buyer. Any surplus will then usually be shared between the buyer and the builder, although the buyer is not usually entitled to recover more than the aggregate of the instalments paid and the supplies purchased. Where, however, there is a shortfall, the builder can demand the difference from the buyer.
Unless they have been excluded by clear words, the builder will also be entitled to rely on its common law rights, which may entitle it to treat the buyer’s conduct as a repudiatory breach of the contract. In such circumstances, the builder can either affirm the contract, or accept the breach as bringing to an end the parties’ respective obligations to construct and purchase the vessel, but require the buyer to pay damages for the builder’s losses.