Facts
Decision
Comment


The importance of the duty to fairly and reasonably draw any particularly onerous clauses in standard conditions to the customers' attention has been highlighted by the High Court in Blu-Sky Solutions Limited v Be Caring Limited, where a party did not review the standard terms when e-signing a contract.

Facts

The claimant, a supplier of mobile phones and telecommunication services, brought an action against the defendant, a social care provider, in which it claimed £180,000 plus value-added tax.

On 14 February 2020, the defendant signed the claimant's order form for the provision of connections for 800 mobile phones. The claimant contended that the contract was concluded when the defendant signed the order form, and that the contract incorporated the claimant's standard terms and conditions (STCs). On 26 February 2020, the defendant emailed the claimant to cancel the order. Pursuant to clause 4.6 of the STCs, an "administration charge" of £225 for each of the 800 connections was payable in the event of cancellation before connection.

Decision

The defendant made several key arguments. It argued that:

  • the STCs had not been incorporated into any contract;
  • clauses 4.6 and 4.8 of the STCs were "unusual or onerous" terms which amounted to penalty clauses and, therefore, were void;
  • the claimant had not suffered any loss due to the cancellation of the defendant's order; and
  • the defendant's signatory believed that she was signing the equivalent of a heads of terms and not an "immediately binding agreement".

The judge thought it was irrelevant as a matter of law that the defendant's signatory believed she was signing the equivalent of a heads of terms, where there was no evidence that this belief was communicated to the claimant.

The judge also held that the STCs had been incorporated into the contract because the defendant could have accessed these via the claimant's website when e-signing the contract. Had it done so and had "a reasonably quick look", it would have had "no reason to think" that the STCs were not applicable.

However, the judge decided that clauses 4.6 and 4.8 of the STCs were penal. In reaching this decision, the judge referred to views expressed by Mr Fancourt QC in Vivienne Westwood Ltd v Conduit Street Development Ltd, that the individual obligations within a clause can and should be considered separately and, if appropriate, severed.

The judge noted that clause 4.6 of the STCs, for example, could be divided into four separate subclauses (ie, cancellation, disconnection, downwards migration and upgrading) and that it therefore made sense to ask whether the clause was penal "in its application to the specified situation . . . namely cancellation", as opposed to considering whether the clause was penal as a whole. The judge concluded that the £225 cancellation charge per connection posed "a detriment out of all proportion" with the claimant's legitimate interests. Further, the judge explained that while this was a contract between two commercial entities, the offending terms were concealed within detailed terms and conditions, making it hard to distinguish "the important from the unimportant". The judge found that the case came extremely close to a misrepresentation.

Given that clauses 4.6 and 4.8 of the STCs were both found to be penal, the judge held that they had not been incorporated into the contract since they were "unduly onerous" and had not been "fairly and reasonably drawn to the defendant's attention". Further, even if they had been incorporated into the contract, they were void. In addition, the judge decided that it was "not possible" for the claimant to have made a confident representation that the defendant would not have to pay any additional charges (the judge also held that such a representation was made negligently) and so any claim for damages would have failed.

Comment

This decision reinforces the importance of drawing a customer's attention to any onerous terms in the standard terms, even where the contractual relationship is between commercial entities and there has been ample opportunity for the customer to access and consider the STCs. If a particularly onerous clause is not highlighted, this could amount to misrepresentation.

It also serves as a warning to customers when e-signing contracts. Incorrect belief as to the nature of a document is not likely to be considered a relevant reason for not taking appropriate steps (eg, reading accompanying documentation). In the world of hybrid working, it can be all too easy to simply "click to sign" without taking the time to navigate through the various platforms and links available (in this case, clicking through to the STCs on the claimant's website).

For further information on this topic please contact Connie O'Conor or Simon Hart at RPC by telephone (+44 20 3060 6000) or email ([email protected] or [email protected]). The RPC website can be accessed at www.rpc.co.uk.