Search results
Order by most recent / most popular / relevance
Results: 1-10 of 12
Would I lie to you?
- RPC
- -
- United Kingdom
- -
- October 7 2009
The court held that, where a contractor had misled the client in order to secure the contract, that amounted to fraudulent misrepresentation, rendering the contract voidable
The importance of full compliance with Pre-Action Protocols
- RPC
- -
- United Kingdom
- -
- October 7 2009
The TCC has made it clear that any parties failing to comply with the spirit as well as the letter of the Pre-Action Protocols will face serious costs consequences when and if the dispute reaches court
How long do I have to challenge an award?
- RPC
- -
- United Kingdom
- -
- October 7 2009
In Jim Ennis Construction Limited v Premier Asphalt Limited 2009 EWHC 1906 (TCC), the TCC had to decide, for the first time, the issue of the nature and date of accrual of the cause of action where a losing party to an adjudication brought under Part II of the Housing Grants, Construction and Regeneration Act 1996 (HGCRA) subsequently commences court proceedings to seek a final determination of the matters decided by the adjudicator, with a view to recovering monies paid to the winning party in compliance with the adjudicator’s decision
When does the right to set-off exist?
- RPC
- -
- United Kingdom
- -
- October 7 2009
In Workspace Management Ltd v YJL London Ltd 2009 EWHC 2017 (TCC), the court had to decide whether a contractor was entitled to set off an adjudicator’s decision in its favour against sums it was obliged to pay the employer under an arbitrator’s award relating to the same contract
Adjudication: nomination of adjudicator
- RPC
- -
- United Kingdom
- -
- June 30 2009
The TCC decision in Bovis Lend Lease Ltd v Cofely Engineering Services 2009 EWHC 1120 provides a reminder that, where the contract stipulates how an adjudicator is to be nominated, strict compliance is required
JCT 2009 revisions
- RPC
- -
- United Kingdom
- -
- June 30 2009
On 18 May 2009, the JCT published the first in a series of revisions to its 2005 standard form building contracts and associated documents
Causation: reasonableness of settlement
- RPC
- -
- United Kingdom
- -
- June 30 2009
The recent TCC decision in Siemens Building Technologies FE Limited (Part 20 Claimant) v Supershield Limited (Part 20 Defendant) 2009 EWHC 927 provides a good example of the difficulties that can arise where a claim involving numerous parties in a contractual chain is settled
Adjudication: natural justice
- RPC
- -
- United Kingdom
- -
- June 30 2009
Withholding notices continue to cause problems
Adjudication: enforcement
- RPC
- -
- United Kingdom
- -
- June 30 2009
What happens when a court is asked to enforce two different decisions reached in separate adjudications that decided different things but which might or do impact on each other?
Ordering costs in the small claimsfast track
- RPC
- -
- United Kingdom
- -
- April 12 2010
Two recent cases argued consecutively in the Court of Appeal address the issue of when it is appropriate for a costs judge to order that costs be assessed on the small claimsfast track basis
