Search results
Order by most recent / most popular / relevance
Results: 1-10 of 11
Judge puts precedence clause in its place!
- Mills & Reeve LLP
- -
- United Kingdom
- -
- May 9 2013
Parties often include a precedence clause in contracts to make sure that, in the case of discrepancies between the various documents which comprise
Alan Sugar, a flock of sheep, an iron paddle-wheel steamship and performance bonds
- Mills & Reeve LLP
- -
- United Kingdom
- -
- April 3 2013
What do Alan Sugar, a flock of sheep and a paddle-wheel steamship have in common? Answer: the recent Court of Appeal case between Aviva and Hackney
Pricing in target cost contracts
- Mills & Reeve LLP
- -
- United Kingdom
- -
- February 28 2013
The Technology and Construction Court has recently commented on the costs the Employer is required to pay under a target cost contract. The Employer
Liquidated damages - be careful how you draft them
- Mills & Reeve LLP
- -
- United Kingdom
- -
- July 30 2012
Over the last few years, the courts have shown themselves to be increasingly unwilling to interfere in the level of liquidated damages set in building contracts
Adjudication enforcement - no breach of natural justice
- Mills & Reeve LLP
- -
- United Kingdom
- -
- March 26 2012
A claim of breach of natural justice failed recently as a contractor sought to avoid enforcement of an adjudicator's decision in favour of its piling sub-contractor
Why wouldn't a sub-contractor have to progress works regularly and diligently?
- Mills & Reeve LLP
- -
- United Kingdom
- -
- January 24 2012
The courts recently held that there was no implied term in a contractor's contract with its sub-contractor that the sub-contractor had to progress the works regularly and diligently
Razing the roof
- Mills & Reeve LLP
- -
- United Kingdom
- -
- October 27 2011
Broster raises the bar for claims in tort based on the complex structure theory
Concurrent delay where are we now?
- Mills & Reeve LLP
- -
- United Kingdom
- -
- September 7 2011
When works run late the employer and contractor need to know who is responsible and whether the contractor is entitled to an extension of time or whether the employer can claim liquidated damages
The duties of the quantity surveyor
- Mills & Reeve LLP
- -
- United Kingdom
- -
- March 16 2011
The Dhamijas appointed the contractor, Sunningdale Joineries, under a JCT IFC 98 form of contract
Beware claims for interest and adjudication they don’t necessarily go together!
- Mills & Reeve LLP
- -
- United Kingdom
- -
- September 7 2010
The courts (and arbitrators) have the power to decide whether a party is entitled to interest on its claim
