Search results
Order by most recent / most popular / relevance
Results: 11-20 of 45
Adjudication: dispute resolution provisions in GC Works1
- Norton Rose LLP
- -
- United Kingdom
- -
- May 25 2010
In the following case, the court considered the meaning of the dispute resolution clause in the GC Works1 Form of Contract; and the use of Part 8 proceedings during an adjudication to seek a declaration that the adjudicator had no jurisdiction to hear the dispute
Adjudication: mistake in adjudicator’s decision
- Norton Rose LLP
- -
- United Kingdom
- -
- February 22 2010
As noted in our report on Rok Building Limited v Celtic Composting Systems Limited (No 2) 2010 EWHC 66 (TCC), the general position is that the court will enforce adjudicator's decisions even if the adjudicator has made an error, unless the adjudicator had no jurisdiction to decide the dispute or there has been a breach of natural justice
Adjudication and arbitration: set-off
- Norton Rose LLP
- -
- United Kingdom
- -
- September 28 2009
The issue before the court in the following case was whether an entitlement to a sum of money under an adjudication award could be used to offset the payment of a sum of money arising out of an arbitrator’s award
Limitation Act, adjudication and court proceedings
- Norton Rose LLP
- -
- United Kingdom
- -
- September 28 2009
The court in the following case had to consider the date of accrual of a cause of action in proceedings brought by the losing party to challenge the adjudicator’s decision
Adjudication: set-off and successive adjudications
- Norton Rose LLP
- -
- United Kingdom
- -
- October 27 2009
It is well established that the purpose of the Housing Grants, Construction and Regeneration Act (Construction Act) was to introduce a mechanism for the prompt settlement of disputes in construction contracts on a provisional basis
Enforceability of reasonable endeavours obligations
- Norton Rose LLP
- -
- United Kingdom
- -
- October 27 2009
An obligation upon a party to use or exercise "all reasonable endeavours" is often used in contracts
Termination: injunction to prevent termination
- Norton Rose LLP
- -
- United Kingdom
- -
- January 27 2010
In the following case the court had to consider whether to issue an injunction to prevent termination of a sub-contract prior to the outcome of an adjudication and whether to issue an injunction preventing a sub-contractor taking any further steps in an adjudication on the basis that it had already embarked on mediation
Letters of intent and contract formation
- Norton Rose LLP
- -
- United Kingdom
- -
- April 27 2010
We reported on the perils of beginning work without agreeing the precise basis upon which it is to be done in both our June 2008 Updater report on RTS Flexible Systems Ltd v Molkerei Alois Muller GMbh & Co KG 2008 EWHC 1097 and our March 2009 Updater report on the Court of Appeal decision in the same case
Adjudication: decision declaratory or a requirement to pay
- Norton Rose LLP
- -
- United Kingdom
- -
- December 21 2009
As reported previously, (October Updater report on Hart (ta D W Hart & Son) v Smith & Anor) a key purpose of the Housing Grants, Construction and Regeneration Act 1996 (Construction Act) was to introduce adjudication to enable the prompt settlement of disputes in construction contracts on a provisional basis
Adjudication: natural justice and bias
- Norton Rose LLP
- -
- United Kingdom
- -
- December 21 2009
Jurisdictional challenges on adjudication enforcement proceedings can be many and various
